task n. 1.(派定的)工作,任务,功课。 2.艰苦的工作,苦差使。 3.〔废语〕租税,税款。 set (sb.) a task 派(某人)一个任务。 be at one's task 在做着工作。 It's quite a task to figure out 10 problems in an hour. 一小时内算出十道习题可是个艰苦的工作。 bring [call, take] sb. to task (for doing sth.) (为…)责备(某人)。 take a task upon oneself 接受任务。 vt. 1.派给工作。 2.虐待,使作苦工。 3.〔废语〕课税。 task one's energies 尽全力。 taskbar 【计算机】(通常显示于电脑屏幕底部的)任务栏。
Building the walls would not be a predecessor task for hanging the clocks , but would be a predecessor task for painting the walls “修建墙壁”则不会成为“悬挂钟表”的前置任务,但将是“粉刷墙壁”的前置任务。
By using lag time , you can specify a waiting period , or delay , between the finish of a predecessor task and the start of a successor task 延隔时间是位于前置任务完成日期与后续任务开始日期之间的一段等待时间。
4 . in the lag field , type the lead time or lag time you want , as a duration or as a percentage of the predecessor task ' s duration 4 。在“延隔时间”域中,键入所需的前置重叠时间或延隔时间,以作为前置任务工期的工期或百分比。
On the other hand , if the predecessor tasks happen to start a week earlier than planned , you might end up with a week of dead time in your schedule 另一方面,如果前置任务恰巧比计划提前了一周开始,那么,在您的日程中最终可能会出现一周的空白时间。
If a predecessor task ends up overlapping the constrained task , a resource assigned to both tasks might be overloaded with work on the overlapping days 如果前置任务最终与受条件限制的任务发生重叠,则同时分配给这两个任务的资源在任务重叠期间将过度分配。
Most likely , you ' ve linked many of your tasks with a finish - to - start ( fs ) link , so that the successor task does n ' t start until its predecessor task finishes 很可能您已使用完成-开始( fs )关系链接了很多任务,因此后续任务要等其前置任务结束后才能开始。
For example , if the predecessor task has a duration of 2 days and you want the successor task to begin 1 day before the predecessor task is completed , type - 50 % in the lag field 譬如,如果前置任务的工期为2天,而您希望该后续任务比前置任务的完成时间提前1天开始,则在“延隔时间”域中输入- 50 % 。
4 . in the lag field , type the lead time you want , as a duration ( type a negative number ) or as a percentage of the predecessor task duration ( type the negative completion percentage ) 4 .在“延隔时间”域中,输入相应的延隔时间,可以是一段时间(输入一个负数)或者是前置任务工期的百分比(输入负的完成百分比) 。
If the tasks you linked are not in a consolidated project , an external predecessor task is added to the project containing the successor task and an external successor task is added to the project containing the predecessor task 如果链接的任务不在合并项目中,那么可以将一个外部前置任务添加到包含后续任务的项目中,或者将一个外部后续任务添加到包含前置任务的项目中。
When you delete a task that is linked to both its predecessor and successor tasks with finish - to - start ( fs ) links , microsoft project automatically links its predecessor task to its successor task with an fs link ( by default ) 默认情况下,如果删除的任务与其前置任务和后续任务之间都有完成-开始( fs )链接, microsoftproject会自动用fs链接将该任务的前置任务链接到它的后续任务。